on May 16, 2026, 5:23 pm
The street in Playa Dorada previously had water running almost constantly while the well pump in the rural area was running for up to 18 hours.
With the installation of this new control valve, the water supply will now be adjusted only to the schedules assigned to the central sector, allowing for better water use and helping to improve supply in the higher areas of the rural area and Valle Verde, where many families are currently experiencing low pressure.
In addition to helping better manage water rationing, this valve will also be a great help for future repairs, as it will allow the network to be divided into sectors and prevent the water supply from being suspended in the entire rural and central area due to a single leak or repair, as happened recently on Monday near the church.
Work continues on:
valve installation
line sectorization
leak reduction
improved water distribution
Thank you to everyone for your patience and understanding while these improvements are being made for the benefit of the entire community.
We also take this opportunity to invite all users with outstanding balances to bring their payments up to date, as every repair, valve, material, and improvement to the network represents a significant expense for the drinking water system.
Thanks to the support and payments of our users who are current on their payments, we are able to continue carrying out work to improve the service for the benefit of the entire community.
DRINKING WATER COMMITTEE
EJIDO LA MANZANILLA